Plan Review Copilot
← back
Clauses

A-101 — A 101 Floor Plan

Test: Chicago Dentist / Rev A / architectural / pdf_2d

11 clause(s)

LabelTextPageExtraction method
1 1. Room layout: Vestibule 101 and Waiting/Reception 102 occupy the front (south) portion of the tenant space, adjacent to the primary exit. Office 103 sits opposite Waiting across a shared partition. Restroom 104 (accessible) and Mech/Elec Room 105 occupy the northeast corner of the front zone. Corridor 106 runs east-west and is the common path of travel connecting Waiting, the four operatories (107-109) and Sterilization (110) at mid-building, back to Staff Break (111), Operatory 4 (112) and Storage (113) at the rear. 1 pdf_text
105 105 Mech/Elec 1 pdf_text
110 110 Steril. ARCHITECTURAL NOTES 1 pdf_text
2 2. Corridor 106 clear width is shown as 3'-4" (40") between the Waiting/Office partition and the Mech/Elec Room wall. This is the only corridor serving the rear operatories, Sterilization and Break Room, so it carries the full occupant load calculated on A-102; confirm the 40" clear width against the applicable minimum corridor width for that occupant load before framing. 1 pdf_text
3 3. The Restroom door (104) is shown swinging outward into Corridor 106 at the point where the corridor is already at its narrowest dimensioned width; coordinate with the electrical engineer, who shows Panel EP-1's required clear working space landing in this same stretch of corridor on E-101. 1 pdf_text
4 4. A column is shown at the Grid C/3 intersection near the Sterilization/Storage partition. This architectural plan dimensions that column at 47'-6" from Grid 1 (field-verify), based on existing field conditions encountered during the walkthrough. The structural framing plan (S-101) locates the same column strictly on grid, 48'-0" from Grid 1. Reconcile the 6" discrepancy with the structural engineer before any new partition or casework is set relative to this column. 1 pdf_text
5 5. All partitions are new 3-5/8" metal stud with 5/8" GWB each side, unless noted otherwise. 1 pdf_text
6 6. Existing building shell and structure are by others; verify all dimensions in the field prior to fabrication of any new partition or casework. 1 pdf_text
7 7. See A-102 for the life safety / egress plan and occupant load calculation. 1 pdf_text
8 8. See S-101 for column and structural grid locations, including the Grid C/3 column note above. 1 pdf_text
9 9. See E-101 for Panel EP-1 and EP-2 locations and required clearances relative to these partitions. 1 pdf_text