| Label | Text | Page | Extraction method |
|---|---|---|---|
| 1.1 | 1.1 Cable tray CT-5 is routed through Electrical Room 210 at 3 feet 6 inches above finished floor, crossing the switchgear SG-2 working clearance zone. | 1 | spec_text |
| 1.2 | 1.2 Cable tray CT-8 is routed through Electrical Room 214 along the ceiling, outside the switchgear SG-4 working clearance zone. | 1 | spec_text |
| 2.1 | 2.1 Conduit bank for Data Hall 2 feeders is routed underslab, stubbing up at column line 12. | 1 | spec_text |