CD-7 — FP-101 — Fire Protection (Sprinkler) Plan

Riverbend Family Dental Clinic / Rev C / fire_protection / pdf_2d

6 clause(s)

LabelTextPageExtraction method
1 1. System: wet-pipe automatic sprinkler, NFPA 13, Light Hazard occupancy classification throughout, Ordinary Hazard Group 1 at Sterilization 110. 1 pdf_text
2 2. Sprinkler head spacing per NFPA 13 max. coverage area for Light Hazard (225 SF/head) and Ordinary Hazard Group 1 (130 SF/head). 1 pdf_text
3 3. SP-14 (Sterilization 110) location shown at same ceiling grid cell as HVAC supply diffuser D-6 per M-101 -- relocate one device prior to ceiling installation to maintain min. 3'-0" separation and unobstructed spray pattern. 1 pdf_text
4 4 A B C D VEST. WAITING OFFICE RR MECH/ELEC OPER. 1 OPER. 2 OPER. 3 STERIL. BREAK OPER. 4 STORAGE SP-1 SP-2 SP-3 SP-4 SP-9 SP-10 SP-11 SP-14 SP-17 SP-18 SP-19 SP-14 SHARES CEILING GRID CELL WITH SUPPLY DIFFUSER D-6 (SEE M-101) FIRE PROTECTION GENERAL NOTES 1 pdf_text
4 4. Exit signage and panic hardware quantities per Design Occupant Load noted below; confirm against A-102 Life Safety occupant load calculation. HYDRAULIC CALCULATION / DESIGN BASIS Design Occupant Load (this floor) = 60 PERSONS (per approved space program, used for exit sign / panic hardware quantities and hydraulic demand basis) Design Density: 0.10 gpm/sf over 1,500 sf (Light Hazard) Required Flow: 225 gpm @ 15 psi residual (est.) Water Supply: Existing 6" combined main, per test 6/2026 1 pdf_text
4400 4400 W. City of Ch Permit No Fire Pr Occupan Drawn: J. REVISION A 06/15/26 N SCALE: 1/8" = 1'-0" (SCHEMATIC, NOT TO SCALE) 1 pdf_text