FP-101 — Fire Protection Sprinkler & Standpipe (Demo)

Demo: Data Center Campus (Full Set) / Rev A / fire_protection / spec

3 clause(s)

LabelTextPageExtraction method
1.1 1.1 Sprinkler branch line SP-6 crosses Data Hall 2 at 14 feet 3 inches above finished floor, below the required duct insulation clearance. 1 spec_text
1.2 1.2 Sprinkler branch line SP-9 crosses Data Hall 3 at 12 feet 6 inches above finished floor. 1 spec_text
2.1 2.1 Standpipe riser in the north stair is sized for a minimum residual pressure of 65 psi at the topmost outlet. 1 spec_text