Clause: 1.1
Severity: high
Engine: real / claude-sonnet-5
Tokens: 1536 in / 380 out
Latency: 4449 ms
Called: 2026-08-09 03:28:31

Flag explanation

The low_voltage cable tray for the BMS backbone runs at 3'-0" AFF through Electrical Room 210 directly within the SG-2 working clearance zone required by NEC 110.26 to be a dedicated 42-inch deep space free of other trades' infrastructure. This is a direct physical conflict.

Prompt sent to model

Clause '1.1' (electrical):
1.1 Switchgear SG-2 in Electrical Room 210 requires a dedicated 42 inch deep working clearance, free of any other trade's infrastructure, per NEC 110.26.

Candidate clauses from other disciplines in the same submission (only these may be cited):
[id: 47f5d696-206b-4fb1-be22-5cdb1ff00e4b] low_voltage 1.2: 1.2 Structured cabling tray for the BMS backbone runs through Electrical Room 214 at ceiling height, outside the switchgear SG-4 working clearance zone.

[id: f9d998ce-48e3-4369-95ea-9d497596c4c7] low_voltage 1.1: 1.1 Structured cabling tray for the BMS backbone runs through Electrical Room 210 at 3 feet 0 inches above finished floor, within the switchgear SG-2 working clearance zone.

[id: 12d65fe8-8ea7-4fcd-bef7-cddeeedbc64e] architectural 1.1: 1.1 Door D-21 to Electrical Room 210 swings inward with a 42 inch arc centered 8 inches off the west wall.

[id: f164326c-f35c-4a91-b220-0341d0b973a9] architectural 1.2: 1.2 Door D-24 to Electrical Room 214 swings outward into the corridor, clear of the room's interior wall faces.

[id: da668d04-55bb-4aae-98db-9ef5df737b1b] mechanical 1.1: 1.1 Ductwork DS-11 within Data Hall 2 shall maintain a minimum clearance of 14 feet 6 inches above finished floor to the bottom of duct insulation.

Does this clause create a coordination conflict with any of the candidates above - i.e. do they describe the same physical space, element, or system in a way that is physically or functionally incompatible? Call report_cross_discipline_conflicts with your findings, or an empty conflicts list if there's no real conflict.

Raw model response

{"conflicts": [{"severity": "high", "explanation": "The low_voltage cable tray for the BMS backbone runs at 3'-0\" AFF through Electrical Room 210 directly within the SG-2 working clearance zone required by NEC 110.26 to be a dedicated 42-inch deep space free of other trades' infrastructure. This is a direct physical conflict.", "cited_clause_ids": ["f9d998ce-48e3-4369-95ea-9d497596c4c7"]}, {"severity": "low", "explanation": "Door D-21 swings inward into Electrical Room 210 with a 42-inch arc centered 8 inches off the west wall; depending on the location of SG-2 and the direction of its required working clearance, the door swing could intrude into the dedicated 42-inch clearance zone, which must remain free of obstructions. This should be verified against the switchgear's exact position and clearance direction.", "cited_clause_ids": ["12d65fe8-8ea7-4fcd-bef7-cddeeedbc64e"]}]}