Plan Review Copilot
← back to flags
Audit trail

Reasoning trace

Clause: 9
Severity: low
Engine: real / claude-sonnet-5
Tokens: 1496 in / 355 out
Latency: 4532 ms
Called: 2026-08-09 07:01:09

Flag explanation

Electrical clause 8 generically references coordinating duct bank routing with civil site utilities on C-101, which overlaps with the same crossing issue flagged in civil clause 9, but does not add new conflicting information beyond the specific clash already noted with electrical clause 5.

Prompt sent to model

Clause '9' (civil):
9. Coordinate the water service / duct bank crossing with the electrical engineer; see the site utilities note above.

Candidate clauses from other disciplines in the same submission (only these may be cited):
[id: 2067eb80-f9e2-4803-9e84-7212f0d801d9] electrical 5: 5. The new electrical service duct bank routes underground from the utility connection to the main distribution equipment; see C-101 for the site routing. C-101 notes a crossing between this duct bank and the new domestic water service with no separation called out --
coordinate the required horizontal and vertical clearance between these utilities with the civil engineer.

[id: c0dba465-0fb3-41ea-84f6-239eb774c8d5] electrical 8: 8. Coordinate underground duct bank routing with civil site utilities, C-101.

[id: d85768ef-17e9-4812-b54e-d3cc4d7b2e7f] mechanical 6: 6. Coordinate all duct routing crossing structural beam lines with the structural engineer's bottom-of-steel elevations shown on S-101; see the RA-1 note above.

[id: 5a416975-bb86-431b-9ced-7bb8cda32589] plumbing 9: 9. Fixture connection sizes noted above are for planning purposes; confirm final sizing with the plumbing fixture cut sheets during submittal review.

[id: 7f4a0783-affb-45f0-8c9a-ca258573be07] plumbing 10: 10. Provide floor drain at Mech/Elec Room 105 per code; route T&P relief discharge and any condensate to this drain.

Does this clause create a coordination conflict with any of the candidates above - i.e. do they describe the same physical space, element, or system in a way that is physically or functionally incompatible? Call report_cross_discipline_conflicts with your findings, or an empty conflicts list if there's no real conflict.

Raw model response

{"conflicts": [{"severity": "medium", "explanation": "Civil clause 9 and electrical clause 5 both identify a crossing between the new domestic water service and the electrical duct bank shown on C-101, but neither clause specifies the actual required horizontal/vertical clearance dimension, leaving the separation unresolved and requiring active coordination to avoid an unsafe or code-noncompliant utility crossing.", "cited_clause_ids": ["2067eb80-f9e2-4803-9e84-7212f0d801d9"]}, {"severity": "low", "explanation": "Electrical clause 8 generically references coordinating duct bank routing with civil site utilities on C-101, which overlaps with the same crossing issue flagged in civil clause 9, but does not add new conflicting information beyond the specific clash already noted with electrical clause 5.", "cited_clause_ids": ["c0dba465-0fb3-41ea-84f6-239eb774c8d5"]}]}