Ductwork DS-11 in Data Hall 2 requires 14'-6" clearance to bottom of duct insulation, but structural beam B-14 only provides 14'-0" clear height in Data Hall 2. The duct clearance requirement exceeds the available structural clear height by 6 inches, making it physically impossible to install as specified.
Prompt sent to model
Clause '1.1' (mechanical):
1.1 Ductwork DS-11 within Data Hall 2 shall maintain a minimum clearance of 14 feet 6 inches above finished floor to the bottom of duct insulation.
Candidate clauses from other disciplines in the same submission (only these may be cited):
[id: f293f8e9-335d-46ec-9bd6-fbdeb528c2db] architectural 1.2: 1.2 Reflected ceiling plan for Data Hall 4 requires a minimum 8 feet 6 inches clear from finished floor to the underside of any overhead equipment, duct, tray, or pipe.
[id: 31c0c6f8-2ce0-4848-a79c-a4ed1534ec37] architectural 1.1: 1.1 Reflected ceiling plan for Data Hall 1 requires a minimum 9 feet 0 inches clear from finished floor to the underside of any overhead equipment, duct, tray, or pipe.
[id: b3006913-bda3-46fb-a810-1b8012937fea] fire_protection 1.1: 1.1 Sprinkler branch line SP-6 crosses Data Hall 2 at 14 feet 3 inches above finished floor, below the required duct insulation clearance.
[id: 6df910bd-5ca1-47fc-b6a3-2cc753e73bc4] structural 1.1: 1.1 Structural beam B-14 provides a minimum clear height of 14 feet 0 inches above finished floor within Data Hall 2.
[id: 57d266d8-7540-4012-a959-7ebd1ec2a38c] structural 1.2: 1.2 Structural beam B-19 provides a minimum clear height of 15 feet 0 inches above finished floor within Data Hall 3.
Does this clause create a coordination conflict with any of the candidates above - i.e. do they describe the same physical space, element, or system in a way that is physically or functionally incompatible? Call report_cross_discipline_conflicts with your findings, or an empty conflicts list if there's no real conflict.
Raw model response
{"conflicts": [{"severity": "high", "explanation": "Ductwork DS-11 in Data Hall 2 requires 14'-6\" clearance to bottom of duct insulation, but structural beam B-14 only provides 14'-0\" clear height in Data Hall 2. The duct clearance requirement exceeds the available structural clear height by 6 inches, making it physically impossible to install as specified.", "cited_clause_ids": ["6df910bd-5ca1-47fc-b6a3-2cc753e73bc4"]}, {"severity": "high", "explanation": "Sprinkler branch line SP-6 crosses Data Hall 2 at 14'-3\", which is below the 14'-6\" minimum clearance required for the bottom of DS-11 duct insulation. This indicates a direct physical clash between the sprinkler line and the ductwork/insulation envelope in the same space.", "cited_clause_ids": ["b3006913-bda3-46fb-a810-1b8012937fea"]}]}