Plan Review Copilot
← back to Demo: Dentist
Revision diff

Rev D → Rev E

Demo: Dentist · sheets with no change between these two revisions are omitted

architectural A-101 — A 101 Floor Plan 0 unchanged
ChangeLabelText
added 6 6. Column at Grid C/3 dimensioned 47'-6" from Grid 1 per existing field conditions -- coordinate with S-101 which shows column on grid (48'-0").
added 110 110 STAFF BREAKIROOM
added 101 101 WAITING /IRECEPTION
added 113 113 COL DIM'D @ 47'-6" FROMIGRID 1 (FIELD VERIFY)
added 103 103 RESTROOMI(ACCESSIBLE)
added 3 3. See A-102 for life safety / egress plan.
added 5 5. Corridor 106 clear width shown 3'-4" (40") -- VERIFY code minimum for occupant load served (see A-102 egress calc).
added 104 104 MECH / ELECIROOM
added 1 1. All partitions new 3-5/8" metal stud w/ 5/8" GWB ea. side U.N.O.
added 4400 4400 W. City of Ch Permit No Floor Occupan Drawn: J. REVISION A 06/15/26 N SCALE: 1/8" = 1'-0" (SCHEMATIC, NOT TO SCALE)
added 40 40"ICLR DOOR SWINGSIINTO CORRIDOR GENERAL NOTES
added 2 2. Existing building shell & structure by others; verify all dimensions in field prior to fabrication.
added 4 4. See S-101 for column and structural grid locations.
removed 7 7. See A-102 for the life safety / egress plan and occupant load calculation.
removed 110 110 Steril. ARCHITECTURAL NOTES
removed 9 9. See E-101 for Panel EP-1 and EP-2 locations and required clearances relative to these partitions.
removed 3 3. The Restroom door (104) is shown swinging outward into Corridor 106 at the point where the corridor is already at its narrowest dimensioned width; coordinate with the electrical engineer, who shows Panel EP-1's required clear working space landing in this same stretch of corridor on E-101.
removed 5 5. All partitions are new 3-5/8" metal stud with 5/8" GWB each side, unless noted otherwise.
removed 1 1. Room layout: Vestibule 101 and Waiting/Reception 102 occupy the front (south) portion of the tenant space, adjacent to the primary exit. Office 103 sits opposite Waiting across a shared partition. Restroom 104 (accessible) and Mech/Elec Room 105 occupy the northeast corner of the front zone. Corridor 106 runs east-west and is the common path of travel connecting Waiting, the four operatories (107-109) and Sterilization (110) at mid-building, back to Staff Break (111), Operatory 4 (112) and Storage (113) at the rear.
removed 8 8. See S-101 for column and structural grid locations, including the Grid C/3 column note above.
removed 105 105 Mech/Elec
removed 2 2. Corridor 106 clear width is shown as 3'-4" (40") between the Waiting/Office partition and the Mech/Elec Room wall. This is the only corridor serving the rear operatories, Sterilization and Break Room, so it carries the full occupant load calculated on A-102; confirm the 40" clear width against the applicable minimum corridor width for that occupant load before framing.
removed 4 4. A column is shown at the Grid C/3 intersection near the Sterilization/Storage partition. This architectural plan dimensions that column at 47'-6" from Grid 1 (field-verify), based on existing field conditions encountered during the walkthrough. The structural framing plan (S-101) locates the same column strictly on grid, 48'-0" from Grid 1. Reconcile the 6" discrepancy with the structural engineer before any new partition or casework is set relative to this column.
removed 6 6. Existing building shell and structure are by others; verify all dimensions in the field prior to fabrication of any new partition or casework.